Home | Survey | Payment| Talks & Presentations | Job Opportunities
Journals   A B C D E F G H I J K L M N O P Q R S T U V W X Y Z
Shandong Electric Power
1007-9904
2016 Issue 7
Simulation Study of UHV AC System Based on PSCAD
LI Yudun;WANG Dapeng;ZHAO Binchao;WANG Jun;WANG Fujing;State Grid Shandong Electric Power Research Institute;Huaneng Zibo Baiyanghe Power Generation Co.;Ltd.;
..............page:1-3+17
Orderly Electricity Management Based on Loaded Adjustable Coefficient Identification
LI Lin;DU Ying;LIU Yongchao;CHENG Tingting;LI Juntian;State Grid Shandong Electric Power Research Institute;
..............page:4-7
Study on Relationship Between Corrosion State and Surface Composition for the Galvanized Steel
YAN Fengjie;FENG Changzheng;LI Xingeng;YUE Zengwu;GUO Kai;Material Laboratory of State Grid Corporation of China;Shandong Electric Power Industrial Boiler Pressure Vessel Inspection Center;State Grid Shandong Electric Power Company;
..............page:8-11
A Calculation Method of Transmission Line Parameters Based on RTDS
ZHANG Linlin;TAN Jing;YE Jun;State Grid Tai’an Power Supply Company;
..............page:12-17
Design and Implementation of Disaster Prevention and Mitigation Information System of Smart Grid
LI Dong;SUN Shijun;ZHANG Hao;QU Xiaobai;SUN Xiaoli;State Grid Shandong Electric Power Company;State Grid Jiyang Power Supply Company;
..............page:18-20
Intelligent Analysis and Early Warning System of Meteorological Disaster Risk
YANG Xiaoyu;ZHANG Sheng;WANG Shouqin;SUN Xinde;NARI Group Company Beijing Branch;Central China Power Grid Co.;Ltd.;
..............page:21-24
Communication System Architecture Design for Island Microgrid
DENG Hua;LI Guanglei;SUN Yelong;ZHANG Tingting;ZHAO Peng;State Grid Yantai Power Supply Company;State Grid Shandong Electric Power Research Institute;State Grid Longkou Power Supply Company;
..............page:25-28+45
Analysis and Treatments of Substation Equipment Joints Heating Reason
KAN Ze;HUANG Daojun;LIU Yu;State Grid Anhui Electric Power Maintenance Company;State Grid Anhui Electric Power Company;
..............page:29-33
Relay Protection Maintenance Mechanism of Transformers in Intelligent Substations
MA Wenheng;GUO Lili;WANG Yichao;ZHAO Yao;XU Liufeng;State Grid Pingdingshan Power Supply Company;
..............page:34-37
Research and Development of Intelligent Substation Training Simulation System
ZHANG Feng;GUO Biyuan;ZHU Jing;GAO Qiufeng;CHEN Yuhang;State Grid Fuzhou Power Supply Company;State Grid Fujian Electric Power Company Management Training Center;
..............page:38-41
Discussion on the Fine Commissioning of 350 MW Supercritical Thermal Power Unit
ZHANG Shanpeng;Shandong Zhongshi Yitong Group Co.;Ltd.;
..............page:42-45
Cause Analysis of Internal Discharge for the 500 kV SF6 Current Transformer
LI Bo;LU Lu;JIANG Ziguo;JI Daizhi;LIU Chang;Huanengchaohu Power Plant Co.;Ltd.;
..............page:51-52+64
Construction Management of the Ximeng-Shandong 1 000 kV AC UHV Project
ZHANG Lianhong;State Grid Shandong Electric Power Company;
..............page:53-55
Calculation and Analysis on the Cross Section Bearing Capacity of Foundation Main Post of the Overhead Transmission Line
LI Xingzhou;MA Fengchen;CHEN Ziyuan;LIN Fang;LI Zhicheng;Northeast Electric Power Design Institute CPECC;Shandong Electrical Power Supply & Transformation Engineering Co.;Ltd.;State Grid Shandong Electric Power Maintenance Company;State Grid Yantai Power Supply Company;State Grid Rizhao Power Supply Company;
..............page:56-59
A Smart Balance Moment Derrick of UHV Transmission Towers
WANG Fuhai;HUANG Peng;WANG Baoli;ZHANG Guanghong;CHEN Chaoyong;Shandong Electric Power T&T Engineering Company;Economic&Technology Research Institute;State Grid Shandong Electric Power Company;State Grid Shandong Electric Power Company;
..............page:60-64
A New Settlement Observation Auxiliary Device Used to UHV Projects
TANG Shuang;SUN Zihang;HE Yongjun;LUO Rongjun;DONG Yi;Economic&Technology Research Institute;State Grid Shandong Electric Power Company;Shandong Electric Power T&T Engineering Company;State Grid Zibo Power Supply Company;State Grid Xiajin Power Supply Company;
..............page:65-67
Research on Noise Control Scheme for 1 000 kV Substation
ZHANG Hua;DU Heng;LIU Xiaorui;GAO Wenlong;YANG Yutai;Central Southern China Electric Power Design Institute;State Grid Shandong Electric Power Company;
..............page:68-69+77
Study on Composite Suspension Insulator Strings Used in 1 000 kV UHV Substations
WANG Nana;LOU Fengqiang;ZHANG Cheng;ZHENG Hongbin;YANG Ming;Central Southern China Electric Power Design Institute;Economic&Technology Research Institute;State Grid Shandong Electric Power Company;State Grid Shandong Electric Power Company;State Grid Dezhou Power Supply Company;State Grid Jinan Power Supply Company;
..............page:70-73
Method of Improving the Remote Success Rate for“Three Remote” Switch
ZHANG Chong;ZHANG Qing;TU Xiangcun;State Grid Zaozhuang Power Supply Company;
..............page:74-77
Analysis and Prevention on Tube Burst Caused by Water Plug in Rear Platen Super Heater of Boilers
LIU Ke;LIU Fuguo;HOU Fanjun;LIU Jinglong;ZHANG Limeng;State Grid Shandong Electric Power Research Institute;Shandong Zhongshi Yitong Group Co.;Ltd.;
..............page:78-80